Construction Quality Control of Sloped Roof System & Prefabricated Gutter
Above-ground area: approx. 18,352.00 m²
Underground area: 16,220.41 m²
The 1st and 2nd basement floors: parking garage, equipment rooms, civil air defense area, etc.
The 1st and 2nd basement floors at the main building: equipment rooms, functional rooms, offices, etc.
Building 10#, 1st floor: outdoor hot spring pools, changing rooms, toilets, power distribution area, etc.
Building 10#, 2nd and 3rd floors: guest rooms.
Building 4#: all guest rooms.
North of Building 10: RV area with 46 fixed RVs.
Finished block tiles (Cement Tiles)
Tile battens: 30×30 mm, spacing according to tile specifications
Counter battens: 40×20 mm, spacing 500 mm
35‑mm‑thick C20 fine aggregate concrete leveling layer,
equipped with welded wire mesh Φ4 @ 100×100 mm, tied with Φ10 rebar
Extruded polystyrene (XPS) insulation layer
One layer of 4‑mm‑thick polymer‑modified asphalt SBS waterproof membrane
20‑mm‑thick 1:2.5 cement mortar leveling layer
Cast‑in‑place reinforced concrete roof slab.
Embedded anchor bolts Φ10 @ 900×900 mm, extending 25 mm into the batten layer.

Bottom formwork: 12‑mm‑thick high‑strength bamboo plywood, smooth surface, free of warping, cracking or delamination.
Supports: 80×50 mm wood joists (no serious decay, cracking or warping);
Φ48×3.5 mm standard steel pipes and couplers (no serious rust, bending or cracks).
Vertical poles: 900×900 mm spacing
Horizontal ledgers: 1.5 m spacing
A bottom ledger at 150 mm above ground
An additional ledger along the roof slope directly below the slab to form a grid structure.
A 50×200 mm continuous bearing pad is set under each pole.
Concrete cover thickness
Effective height of slab reinforcement
Overall stability and anti‑stepping performance of the mesh
10–20 mm crushed stone is used for better compaction.
Medium-coarse sand with fineness modulus M = 2.8 reduces water consumption by 20–25 kg/m³ compared with M = 2.3, avoiding a high water‑cement ratio.
Fly‑ash blended cement is used to reduce cement content, improve workability, lower hydration heat, and produce denser, stronger and more durable concrete.
The top form is partially closed, width approx. 1000 mm
A 600‑mm pouring slot is reserved for placing and vibrating
A movable baffle prevents aggregate sliding
Special care is taken at joints with roof vents and at corners, which are vibrated at least two to three times and filled and compacted progressively.
4. Curing
The shrinkage rate before hardening is 10–30 times higher than after hardening.
Lay the horizontal part first, then upwards along the vertical
Fully adhere to internal corners, no voids
Vertical walls fully bonded
Joints rolled compact and firmly bonded
Typical roof: lay main tiles first, then right‑side tiles to maintain a regular edge.
Regular polygonal roof: layout from the center to both sides, cut at the ridge.
Horizontal tying: spaced by one main tile, staggered at laps.
Vertical spacing: 1 m.
Rebar at the ridge must be firmly tied (hook‑bent connection).
Each tile secured with 18# double‑strand copper wire.
Copper wire is passed through tile holes; tiles are bedded in 1:3 cement mortar on the protective layer.
Ridge tiles use bonding mortar for extra strength.
During installation, copper wire is temporarily folded upward;
after the tile is firmly bedded, the wire is tied to the batten.
A horizontal line is stretched to ensure alignment.
Tile surfaces are kept clean; mortar and debris are removed immediately.
Apply a leveling layer
Add an extra waterproof layer
Apply and trowel a protective layer
Prefabricated gutters are factory‑prefabricated based on detailed shop drawings approved and signed by the design institute.
Main steel keel: control elevation, embedded parts and welding quality.
After keel installation, aluminum panels are fixed with Steel nails to avoid warping and provide a smooth surface for membrane lapping.
Sealant between aluminum panels is critical to prevent future leakage.
Protection during construction is required to avoid sealant cracking from stepping.
Care is taken during waterproof membrane installation to avoid damaging panel joints.
After roof waterproofing is completed, extend the membrane 200 mm beyond the eave for later lapping.
During gutter installation, secure aluminum laps and wall‑connected panels to prevent warping; apply sealant evenly.
After keel and aluminum works are finished,
bond the reserved waterproof membrane to the gutter aluminum surface.
This ensures rainwater and seepage under tiles drain into the gutter,
preventing water penetration below the waterproof layer or into insulated walls.
Call us:+86-18632003436
+86-18630061517
Email: info@yinengde.com
whatsapp: +86-18630061517
Copyright @ 2026 Wade New Materials. All rights reserved
This website uses cookies to ensure you get the best experience on our website.
Comment
(0)